Feb 17 - Mar 8

o   Concrete driveway turnaround poured
o   Courtyard poured
o   Kitchen countertops installed 
o   Great Room bookcases installed (not yet stained)

Insulation pads to prevent freezing.

Completing the driveway arc/circle

Courtyard (to be)

Preparation of courtyard - "pack" in place -compacting in progress

Courtyard - Rebar Installed (first half)

Pouring the sidewalk

Half of courtyard completed - exposed limestone aggregate

Preparation of second half of courtyard.  Circle in the center is for stamped and colored concrete "cobblestone" finish.

Great Room bookcases installed - lower cabinet doors on order.  Not yet stained.

Double oven and top of breakfast room TV cabinet

Laundry Room

Master bath vanity

Guest Bath vanity

Center Island with Gas Cooktop and Downdraft fan installed.

End of Center Island

Kitchen Sink

Outer Island with bar sink and counter.

Temporary braces to hold countertop