January 29

o    Kitchen, bathroom, and laundry room cabinet installation is mostly complete.  
o    HVAC complete and operating (all 3 systems) - we have heat in the basement!. 
o    Appliances arrive February 1.  
o    Field measurement for countertops scheduled for February 3.
o    If weather holds out, they will pour the concrete driveway pad (critical path item)
o    Interior doors have arrived.  Work on staining them in progress.

Work on grading continues.  Preparation for the driveway pad underway on the left.

Laundry Room (freezer goes on the right)

Washer and dryer below these cabinets.

Pantry to be (before shelving installed)