o Kitchen, bathroom, and laundry room cabinet
installation is mostly complete.
o HVAC complete and operating (all 3 systems) - we have heat
in the basement!.
o Appliances arrive February 1.
o Field measurement for
countertops scheduled for February 3.
o If weather holds out, they will pour the concrete driveway
pad (critical path item)
o Interior doors have arrived. Work on staining them in
progress.
Work on grading continues. Preparation for the driveway pad underway on the left.
Laundry Room (freezer goes on the right)
Washer and dryer below these cabinets.
Pantry to be (before shelving installed)